on 05-20-2015 6:30 PM
Hi Experts,
After deconsolidation completion, I am unable to see put-away warehouse task.
I can see time delay of 60 in config to create put-away warehouse task. Need your input on this.
Thanks.
Hi Imran
Check in detail tab 2 and check is your decon step is complete flag is set. If yes then check config that u have auto flag applied to your decon step. if not flag it. all other step than last step should be auto wt flag, this will create auto WT as per your presiding activity.
and flow new del for new process.
Complete activity and come back if ur issue is not resolve. also delay if you dont want remove the config.
Regards
Suraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Imran,
Hope you re using POSC and you have checked the check box for Product WT/HU WT next to auto WT check box in your process for your steps. The check box for Product WT should be checked at DECON step or before this step.
Thanks and regards
Anoop
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
is your deconsolidation activity a part of POSC customizing? Can you please share how did you set this step?
Petr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.