Schedule Job for TR import between Development Clients

Former Member
0 Kudos

Hello Basis experts,

We want to schedule hourly basis Job to import TRs between different clients of SAP Development system.Please help out in providing the procedure for the same.

For example we have two clients in Development system Client 100 and Client 200(Copy of 100). The changes made in client 100 needs to be moved to client 200 on hourly basis via job. We dont want to do it manually every time from SCC1 for each and every TR. And need to keep both the clients in sync.

If there is a procedure to schedule a job then please help.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi...Dinesh...Refer this thread ..

You have steps by step process given by..Former Member....

Hope it helps

thanks

Syed

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Dinesh

You have Different options to schedule transports like every hour

TMS jobs must be scheduled via STMS.  To do this:

1) Goto transaction STMS

2) Select 'Overview -> Imports

3) Double click on the system you wish to schedule the job for

4) Click on the truck icon to schedule an import all job (only import

   all jobs may be scheduled as periodic)

5) Fill in target client, if necessary

6) Select "At start time" and fill in the date and time

7) Next to 'Period' there is a box with a gray background.  If you

   click in the box a drop-down arrow will appear.  Click on this.

😎 Select your period from the menu options and click on the green

   check.

9) Click on the green check again and your job will be scheduled.

or

you schedule the automatic import of u_rgent corrections via /TMWFLOW/SCMA_BTCH_SYNC_UC

see this link for more details

http://help.sap.com/saphelp_sm40/helpdata/en/96/0737423df2b26be10000000a155106/content.html

Regards

Ahmed