IW33 - Display PM Order

0 Kudos


Hello,

I'm hoping that someone can help me with this question.

On the Addit. Data tab, where is the Responsible CCtr pulled from?  Is it a manual entry or pulled from another screen?

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

pardhreddyc
Active Contributor
0 Kudos

Dear,

Cost center whichis displaying in additional tab is called "Responsible cost center". This does  not need to be the cost center which order needs to be settled.

Chcek your main workcenter "Costing tab".

Noramally we have two type of cost centers used for PM/Ps oneresponsible and other is requesting cost center.

Responsible cost center is responsible to carry out the work.

Requesting cost center is used to settle the cost of the order.

Regards,

Pardhu

pardhreddyc
Active Contributor
0 Kudos

Dear,

This will be populated from the WORKCENTER master.

Regards,

Pardhu