Process to change BOM Quantity after BOM explosion

Hi,

I want to what is the process that is normally being followed to change the BOM quantity once BOM has been exploded.

I will clarify my point.

I have attached a finished material to the activity and exploded the BOM manually (edit>component>explode).

Now if I want to change the quantity of the header BOM material from (say) 1 to 2 quantity, then how the BOM quantities will get updated accordingly.

e.g. BOM material A has two components B and C.

one A quantity has BOM ---- B is 2 nos. and C say 3 nos.

So if I change the A quantity to 2 nos. after the BOM is exploded then how the quantity of B will become 2X2 = 4 and C will become 6.

What is the process that is normally followed to update the quantity.

Abhra.