Hi,
I want to what is the process that is normally being followed to change the BOM quantity once BOM has been exploded.
I will clarify my point.
I have attached a finished material to the activity and exploded the BOM manually (edit>component>explode).
Now if I want to change the quantity of the header BOM material from (say) 1 to 2 quantity, then how the BOM quantities will get updated accordingly.
e.g. BOM material A has two components B and C.
one A quantity has BOM ---- B is 2 nos. and C say 3 nos.
So if I change the A quantity to 2 nos. after the BOM is exploded then how the quantity of B will become 2X2 = 4 and C will become 6.
What is the process that is normally followed to update the quantity.
Abhra.
Dear Abhra,
Did you get the solution??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Your requirement is fullfill by execution factor in activity level or
Edit > Component > Explode > Requirement Qty.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.