Different vendor use different sample procedure on same material

Hi QM experts,

User asked me a question: Material_01 have two vendor----vendor 1 and vendor 2, and for different vendor will assign different sample procedure, example as following:

Material_01 ----- vendor 1 ----- sample procedure 1

Material_01 ----- vendor 2 ----- sample procedure 2

How to achieve it?

Best Regards,

Bu Fanchao

Former Member
replied

Dear Fanchao,

We can achieve this requirement by maintain the two group counters in the same inspection plan i.e. Group counter 1 should be your first vendor and assign the desired characteristics for the first vendor

second group counter maintain the vendor 2 and maintain the required characteristics

but you have to ensure the valid from date should be lies in your GRN date then only these MIC will flow to your inspection lot

refer the attachment

Regards,

Venkatesh..