Logic for PPM data

former_member225123
Participant
0 Kudos

Hi Everyone,

I am new in PPM, I need to submit one logic for BW report for PPM.

Requirement is like -

List projects phase wise
Sort project on Value wise
Planned versus actual timelines WBSwise
List of resources assigned to Project - Role, days, booked
Total number of purchase orders & values of orders exceeding delivery days per project/WBS
Resources overloaded - list(employees)
Roles not staffed- list

Please suggest me such kind of logic we may find from ECC or standard reports may be call if any to show such data.

Regards

Gaurav Ahuja

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member225123
Participant
0 Kudos

Hi Judith,

I search SCN & get to know about LaunchPads ( LPD_CUST ), I can see many queries there which may help me in finding data. Can u please assist how we can make use of them, Can i execute queries there as well ?

Regards

Gaurav Ahuja

judith_gabriel
Contributor
0 Kudos

Dear Gaurav,

the Launchpad customizing is only relevant for navigation. (for example links to objects, transactions,...)

Best regards,
Judith

judith_gabriel
Contributor
0 Kudos

Dear Gaurav,

the available datasources which are used for BW-reporting can you find as follows:
- Call transaction RSA3
- Datasource: 0RPM*
- Call the input-help.

Best regards,
Judith

former_member225123
Participant
0 Kudos

Hi Judith,

If i need this data, will i get these details from available data sources?

List of resources assigned to Project - Role, days, booked

Resources overloaded - list(employees)
Roles not staffed- list


Regards

Gaurav Ahuja

judith_gabriel
Contributor
0 Kudos

Dear Gaurav,

you can find the datasources of Projectmanagement by searching with 0DPR* in RSA3.
The following one can help you:

0DPR_PART_PROJECT_LINK  Assignment of Project Roles to Project
0DPR_RESOURCE_PROJECT_LINK Assignment of Resource to Project
0DPR_PARTICIPANT_DATE  Dates for Role

0DPR_PART_BUPA_LINK  Staffing of Project Role with Business Partner
0DPR_PARTICIPANT_OBJECT_LINK Object Links for Role
0DPR_PART_ATTR   Role Attributes

Concerning the "overloaded Resources" you can use the "Resource Management".

Best regards,
Judith

former_member225123
Participant
0 Kudos

Hi Judith,

Thanks. It is really helpful.

How can i use resource management here, Is there any other data-sources for resource management as well ?? how can i find this logic or data in ECC..

Regards

Gaurav Ahuja

judith_gabriel
Contributor
0 Kudos

Hi Gaurav,

the "Resource Management" functionality is available in the Frontend as "Portfolio management", "Project Management".
Information can you also find in the online help:
Project Resource Planning (Portfolio Management) - SAP Portfolio and Project Management - SAP Librar...

Best regards,
Judith