Dear all,
how to Exclude the Planned Delivery time & GR Processing time In Schedule agreement During LTP execution for Specific planning scenario (20).
Due to above consideration there is a date shift in order start date and finish date.
Is there any config ?
For example: Material : X (Procurement Key is E) PIR made for 100 nos on 13.05.2015 Type is (PD)
Material : Y (Procurement Key is F) which is procured from vendor ZZZZ Which is the immediate child of Matl X in BOM where Type is (PD)
Via T code : MS02 for planning scenario 20 for material X LTP is executed.
Planned Order generated for Material : X on 13.05.2015
But for Material Y Purchase requisition for Material : Y on 11.05.2015 for qty 100 nos to vendor ZZZZ
Because in Schedule agreement for Planned Delivery time is 2 days
Where strategy group is 10 for both materials X and Y.
Requirement :
Material Y Purchase requisition for Material : Y should on 13.05.2015 Itself.
Regards,
U.linganathan.
Hello
This is not possible on standard but you can use BAdI MD_MRP_PARAMETERS.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.