LTP Exclude Time for Plannig scenario -->20 Only

Dear all,

how to Exclude the Planned Delivery time & GR Processing time In Schedule agreement During LTP execution for Specific planning scenario (20).

Due to above consideration there is a date shift in order start date and finish date.

Is there any config ?

For example: Material : X (Procurement Key is E) PIR made for 100 nos on 13.05.2015 Type is  (PD)

Material : Y (Procurement Key is F) which is procured from vendor ZZZZ Which is the immediate child of Matl X in BOM where Type is  (PD)

Via T code : MS02 for planning scenario 20 for material X LTP is executed.

Planned Order generated for Material : X on 13.05.2015

But for Material Y Purchase requisition for Material : Y on 11.05.2015 for qty 100 nos to vendor ZZZZ

Because in Schedule agreement for Planned Delivery time is 2 days


Where strategy group is 10 for both materials X and Y.

Requirement :

Material Y Purchase requisition for Material : Y should on 13.05.2015 Itself.

Regards,

U.linganathan.