Hi All,
We are facing problem while rescheduling orders in DS planning Board.
The error exists only for Production Order(Release).
The error says as- "Activity is in the fixing interval of resource or outside the planning period."
Please help.
Hello Pratibha,
Please check the planning period in DS board An operation that you want to schedule must lie within the planning period. You cannot schedule or reschedule operations that lie outside of the planning period;
Before you can reschedule a fixed operation, you must first undo the fix for this object.
You can also create, replace, or delete fixing intervals using the heuristic SAP_DS_03.
Please refer these links,
Defining the Planning Period - Detailed Scheduling Topics - SAP Library
Fixing Operations, Orders, and Time Intervals - Detailed Scheduling Topics - SAP Library
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This issue can happen if the resource of the activity for which the error message is raised is outside the Propagation Range.
Before opening the DSPB, you may want to click Profiles... button, then go to More Profiles tab, and set Propagation Range SAPALL.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.