Hi Pradeep,
it is your backward scheduling so system start calculate from requested delivery date 18/05/2015 so that to full fill this requirement material should available on date 14/05/2015.
If you want current date should be your material available date then modify the requested delivery date to near future as per your different lead time like- transit lead time, Loading time, Pick and Pack time, so that it will fall available date is 12/05/2015 and system will check availability on 12/05/2015.