Hi Experts

During GRC 10.1 ,ARQ implementation i encountered a error as below.

I changed the validity dates and i was able to submit the request.Please let me know if anyone as encountered the issue before and what the cause and soluion of the issue.

Thanks

Nitesh

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member197694
Active Contributor
0 Kudos

Hello

check the below Note and apply as per your SP

2119407 - UAM: Incorrect validity dates when business role is added in the simplified access request


2042631 - Validity Dates for Business Roles


1979538 - Simplified Access Request Role Validity Dates Validation Error messages


Regards

Baithi

former_member218247
Participant
0 Kudos

Hi Baithi

I am not using simplified Access Request.

Thanks

Nitesh

former_member185447
Active Contributor
0 Kudos

Hello Nitesh,

If you are requesting for a FF ID, then it seems the date is getting pulled from the parameter 4001 which contains the default days for FF ID and it seems it is not updating the user buffer with the dates that you are changing.

If that is the case, this SAP Note will help you 1709528.

Regards,