Hi,
Please let me know where scheduling offset, scduling value of an planned order/ process orders is saved in SAP APO?
How can I update the above values for an existing process order in SAP APO - PP/DS?
Thank you in advance.
Regards,
Surajit Das
Hi Surajit,
The scheduling offset is stored with the input and/or output details of the order, in the liveCache.
You may display the order details in the liveCache as per document below:
The scheduling offset for each i/o node can be seen in ET_INPUTS / ET_OUTPUTS, field OFFSET_VALUE.
A possibility to update the scheduling offset is to reexplode the existing orders. If the PDS contains the updated values, they will be updated in the order.
Best regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.