on 05-11-2015 8:09 AM
Hello,
After doing IM52, the budget gets distributed correctly.But the same is not correctly displayed in reports.I expect if the original budget was for 100 and supplement was for 50 , the reports (project) should show me 150- but it does not so show.Do i need to do something in project reports.
Rgds
SRJ
Hello,
Any project report like S_ALR_87013558 can be seen .In Budgeted values , the supplementary budget values are not added to original values.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please send some screen shots for the budget reports you have executed.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi SRJ,
can you share your screenshot shot what ever you are saying here?
which report you are executing to see the total budget in IM module?
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Which report are you checking the budget? Can you share the report screen shots??
Regards
Sammar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.