Planning board color

Former Member
0 Kudos

Hello Experts,

I have a requirement that the users want the background for weekend days to be grayed out. This is not downtime but the users would like to be able to easily identify weekends from week days. Currently the planning board does not have any background color for weekend days (Sat and Sun). Please advice how to change the background color for just weekend to gray without maintaining downtimes

Thank you

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Ganpath,

Non working days will be always in gray out colour, Please check the factory calendar in resource RES01 it should be five days working, Or you can have capacity variant with 5 days shift sequence.