Date fixing of purchase req in APO PPDS

former_member309586
Participant
0 Kudos

Hi Gurus,

Can anyone please suggest how to fix date to all purchase req generated during the period in PPDS?

Business wanted to fix date for purchase req to have correct number to the lower level.

Please suggest

Thanks & Regards,

Rajesh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi RK,

You can try to fix dates in the DS planning board.

The function exist if you right click on the order and choose in the context menu the function FIX order. For mass fix you can create a button "FIX" which will call function SL26.

Thanks,

Regards, Marius 

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rajesh,

Do you mean FIRMING the requisition?

I presume you are planning for components in APO.

If you want to firm the requistion from any automated changed, kindly go through the below thread.

https://scn.sap.com/thread/1212701

Hope it helps.

Regards,

Sandeep

former_member309586
Participant
0 Kudos

Hi Sandeep,

Thanks for your response. I am looking for date fixing in PPDS for purchase reqs.

It will be helpful if you can suggest some thing where we can fix the "date fixing".

Thanks & Regards,

Rajesh