MD61 Question

Hi Experts,

When i enter PIR in MD61 (period : Weekly), the systems put the requirement at the first day of the week.

I want to put it at the end of week, Is it possible?

I use FX for my material lot sizing.

I've tried to set in OMI4 ( scheduling = 2 : Period end : delivery date), but entered in this field not allowed.

Please help me.



Dear Yohanna,

You can do one thing that put your lot size as WB and enter Maximum lot size and minimum lot size as same.

And change scheduling as according to your need.


Saurabh kumar