on 05-03-2015 7:35 AM
Dear all,
I have created a project with some activities and wbs elements where a progress version is assigned to the activities. The planning and actual measurement methods are 'time proportional' and 'work' in the assigned progress version. I want to obtain a monthly plan of the project progress but I dont know how to do this.
consider the start of the project is 01/05/2015 and i want to obtain the project progress plan at the end of the months 05, 06, ... until the end of the 2015 year:
30/05/2015 x1 %
30/06/2015 x2 %
30/07/2015 x3 %
30/08/2015 x4 %
...
I try it by cne1 and cne 5, but it does not give me the plan poc of the project monthly but it calculates only the poc for the first activity in the network. I think it works based on the current date.
Please give me some guidance on this issue and clear me how can i obtain the plan progress of project at the end of each month.
Regards
Hi,
could you check progress content is configured in your system as per below instruction.
define progress version as 0
define measurement method - cost /time proportioned
object type dependent default value for measurement WBS, Activity Plan/Actual
assign progress cost element cost element category would be 61
if you are using SKF then
CJS2 for planing SKF
KB31N enter SKF to wbs object
CNE1/CNE5 for reporting progress check.
POC will calculate based on Planed qty /Actual qty/overall planed qty*100
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
thanks for reply. I have configured those as follows:
progress version 0,
measurement method time proportional/work for plan and actual and defaulted them
and assigned cost element 6511.
As I said before our client requirement is to obtain the monthly (plan) project progress at the beginning of the project. I tried it by giving different periods in CNE1, but it does not affect the results and i can not achieve this.
Please suggest a solution to this issue.
Regards
Hi Sanjeev,
Sorry if my question is not clear. (please look at the example) I dont have any problem in actual poc, bcws , ... and i can see the actuals when i confirm activities. I want (as in the original post) a plan of the monthly progress of project at the beginning. I restate the above example:
consider the start of the project is 04/05/2015 and i want to obtain, now, what would be the project progress plan at the end of the months 05, 06, ... until the end of the 2015 year:
30/05/2015 x1 %
30/06/2015 x2 %
30/07/2015 x3 %
30/08/2015 x4 %
.
.
.
I give periods 05, 06, ... in CNE1 for progress calculations but it does not work.
how to achieve the requirement?
Regards
I suggested how progress can be check and updating in standard sap system and based on above parameter it should be work but as you said its not updating so let me know what you are doing
like you have created project today and plan updated by which transaction in wbs based or activity based?
and what you have done for actual like system how to know the actual or what basis system calculate the progress? if you are executing without done any activity on project object like today project creation then run progress check report. then how system will update the progress?
so please share your process and screenshot what you are doing?
Regards,
Sanjeev
Hi,
May I know why you require only on the last day of the month? Can you please let us know your business requirement in detail?
Regards,
Sesha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks for reply
this is the requirement of out client and I want to obtain the monthly plan progress of project at the beginning of project. our client want to know the monthly (planned) project progress at the beginning of project and then he want to compare it at each month with actual progress.
Regards
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.