on 05-02-2015 8:29 AM
Hi Experts,
This is regarding Target cost column in KKF6N.
I am checking KKF6N Cost tab for one material
There are 3 columns. Target Cost, Actual Cost and Variance.
I understoo entire process for Actual cost and its working fine.
But for Target cost i am not sure from where the values are flowing. For example i have maintained activity type rate for Labour hour as 100 so when we put 44 hours in actual cost it is coming as 4400, but in Target cost column it is coming as 2250. I am confused as how is this coming because this varince will be posted and values will posted wrong at variance calculation.
Please guide
Regards
zunaid
Hi
Target cost is std cost x actual quantity and as rightly said by Kamal ji, is populated after GR.
Please don't forget to close the thread if satisfied.
Rajneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Zunaid,
Basically target costs is planned costs adjusted with actual costs. Here system will calculate target costs as (Total plan quantity/Total plan qty*total actual qty)* actual rate.
Regards,
Mukthar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
At the time GR target cost is triggered
kamal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.