Hi,

We are planning do to system copy for PI7.1 system from PRD to QUA.  I am trying to find some SAP Notes for Post steps.

what are the major post steps to perform in system copy apart from Background job suspend , cut the RFC connection and configuration wizard,etc..

I have gone throug below notes, but still i need more information about the communication channel to de-active and how I can bring the step of QUA.

1299373 - Configuration Wizard: PI System Copy

1400543 - Configuration Wizard: PI Robustness

1309239 - Configuration Wizard: PI NetWeaver initial setup

Platform: SAP PI7.1

OS        : AIX

Database : Oracle 11G

Appropriate information are really appreciate.....

Thanks,

BM

Accepted Solutions (0)

Answers (2)

Answers (2)

Sriram2009
Active Contributor
0 Kudos

Hi

Kindly refer the system copy guide from http://service.sap.com/guidefinder - select the OS /DB & SAP version

BR

SS

Brindavan_M
Contributor
0 Kudos

Hi Sriram,

I have already visit this site and downloaded the document as well , but I have not get the information which I am excepting....

Thanks,

BM

Sriram2009
Active Contributor
Former Member
0 Kudos

Hi Brindavan,

you can follow up on below steps we normally follow in general:-

Basic Tests for Java
Java Component Check
Testing the availability of the PI JAVA applications
Testing of Internet Communication Manager
Queue Registration
Testing of the Web Service Runtime
SLDCHECK
Testing the HTTP services on the Integration Server
RFC Connections
Testing the connection to the Integration Builder
Cache Connectivity Test
SXI_CACHE
Adapter Engine Connection Data Cache
Testing the CPA Cache
Testing the connectivity between Enterprise Service Repository and SLD
Testing the connectivity between Integration Directory and Enterprise Service Repository
Advanced Check: Testing cache notifications of the Integration Directory
Communication Channel Monitoring
Message Monitoring via Status Overview Page
Configuration and Monitoring
Service Registry
Background jobs running on the SAP Web ASABAP
Background jobs running on the SAP Web ASJava
ccBPM monitoring
Readiness Check on Advanced Adapter Engine Extended (AEX)
Test message to Integration Server
Test message to Adapter Engine
SLD Associations
Configuration of HTTP Load Distribution with more than one Application Server
Small Scenario
Configuration Test of scenarios in Integration Directory

Let us know if this helps you for your refresh activity.

Regards,

Ram

Brindavan_M
Contributor
0 Kudos

Hi Ram,

Thanks for the some steps to check, but my question is there are thrid party connection will exit after refresh from production and lot of communication channels are configured.So QUA should connection those system to pick any real time data will cause major issue. Therefore I need to revert back the setting in QUA connection like FTC etc.. should connect like before after refresh. provide those kind of information if you have...

Thanks,

BM

former_member185954
Active Contributor
0 Kudos

Hello BM,

you can use Channel Availability Timings configuration to stop key third party related channels to ensure no data is being transferred during copy.

Planning Availability Times - Process Integration Monitoring - SAP Library

Use the URL to experiment

http://<prod pi host>:5xxx/mdt/channelmonitorservlet