Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Production Order Expected Yield Variance

Hello All,

Can someone please tell me why I am getting an expected yield variance during order confirmation using CO11n?  There are no Goods Receipts or goods movements taking place.  We only use CO11n to confirm Labor hours based on yield.  This does not occur for all orders only some.  I also have updated the delivery tolerances, there is not assembly scrap in the materials master or the routing.  We do the actual goods movement using MIGO.  The control type is not set for auto goods receipt because we are not receiving material at this level.  Do I need to implement a scheduling profile for all materials even though they are not warehouse managed and Goods receipt and Goods movements are not being performed?

Thanks in advance for your help

Not what you were looking for? View more on this topic or Ask a question