PDS showing wrong validity date

Former Member
0 Kudos

When i am transferring  PV's from ECC to APO the validty date is showing wrong

Suppose my end validity date is 22/04/2015 .when i am doing curto_create no errors is getting  but it is showing 23/04/2015. one day advance in APO

what could be reason

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello Virendra,

As i Know during PDS integration the validity dates are converted from local time zone of the plant in which the production version exists to UTC

Please refer Comparison of PP/DS Production Data Structure - Integration via APO Core Interface (CIF) - SAP Libra...

Best Regards,