Dear All,
I have some requirement in the equipement calibration as given below.
1) Next call date should be less than 1 day for the next call . Means if my cycle time is 1 month, and start of cycle is on 15th then next plan date should be 1 day before, next call should be on 14 of next month and further moving ahead it should be on 13 on the next month and so on. Is it possible in standard SAP or any custom development.
2) Next call date should be based upon the UD date. Means if my cycle time is 1 month, and start of cycle is on 15th. Now in this case if i completed inspection lot processing on 20th then next call should be calculated based upon the UD date and it should be 20th of next month.
How these two scenerio can be handled.
Regards
Amit
Hello AMIT,
The first requirement can be achieved by setting Call Horizon as 96% or 97% in the maintenance plan. For he second requirement, you may have to use the user-exit IPRM0002, with the help of your ABAPer.
Regards
KJogeswaraRao
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jogeswara,
Thanks for the updates.
Just want to ask you another query that, in case of fixed date scheduling
system will generate the call on fixed date of each month. e. g every 15th day
of each month in case of monthly schedule. But if I started the schedule on
31st then system will generate the next call on 30 of next month and it will
call on 28 in case of Feb month and then it will continue to generate calls on
28th date only. But my business requires to generate call in the
last day of the month.
In this scenario how to handle the situation.
Regards
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.