Hi,

The problem I facing currently during transport of SAP business system from Dev to Quality system, logical system  is missing in the Adapter Specific parameters.

The actual problem I have seen in the SLD, the logical system is a blank and even after I pushed from RZ70.

Can you please suggest me how could i retrieve the Logical system in the SLD by automatically.

Thanks in advance.

Best Regards,
Sateesh

Accepted Solutions (1)

Accepted Solutions (1)

Harish
Active Contributor
0 Kudos

Hi Sateesh,

you can run the report SAI_CACHE_REFRESH in PI and ECC. also refer the below SAP note

1740953 - Logical system Name vanished in Business System of SLD

Former Member
0 Kudos

Hi Azhar, Hi Mistri,

Thanks for your replies.

currently I see the problem on PI system while updating technical information into SLD. I do see logical system name of PI system not appears into SLD after update.

Due to this all adapter specific parameters of business systems not appears in the Integration directory.

Best Regards,
Sateesh N





Former Member
0 Kudos

Hi,

We resolved the issue, we found in t.code SCC4 the client has not assigned to logical system.

We assigned and push to SLD using RZ70, now Logical system appears in the SLD.

Thank you.

Sateesh

Answers (1)

Answers (1)

azharshaikh
Active Contributor
0 Kudos

Hi Sateesh,

Please check the following links for similar issue , if it helps:

Also, you can enter the Logical Name in the SLD, for the related TS / BS.

Regards,