Original production order start dates


I am trying to determine the original start and finish dates of production orders in SAP ECC.  We use SAP ECC and APO for advanced planning and optimization;  our start dates never go into the past so it is impossible (to my knowledge) to tell if we are starting production orders on time or not.  I have checked forums and have not found any helpful threads.  I have also tried t-code "Co03" and chose; Header>status changes and did not see anything relating to production order start date.  Any help would be appreciated, thank you.


Helpful Answer