This is quite a simple question.

Is it possible to hide/filter projects in SOLAR_PROJECT_ADMIN (to limit the number of projects you can view) but the projects are still visible in SOLAR01 and SOLAR02?

I have marked completed projects as RELEASED in SOLAR_PROJECT_ADMIN and then clicked on Settings>Cross Project>Hide Finished Projects

This indeed hides the projects that are RELEASED but then we can't view these in SOLAR01/02. Our requirement is to hide in SOLAR_PROJECT_ADMIN but still be able to view in SOLAR01/02.

Is this possible?




Hi Shaun,

You can use solman_workcenter->Implementation/Upgrade workcenter and can define your own queries to see the project which are open or not finished etc.

There is no option other than you have already mentioned of HIDE FINISHED projects in solar_project_admin.

Therefore, I would recommend start using Solman_workcenter which is pretty much matured now and can be further customized as per your requirements.

hope this helps.