Confirmed qty shd be full with no stock VA01

Former Member
0 Kudos

Hi friends,

Our requirement is that when Sales Order is created with VA01, system should confirm the full qty even if there is no stock. But at the same time, requirement should pass to MD04. If there will be no stock at the time of Delivery then system will give error- that is ok. Pl suggest.

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

former_member182378
Active Contributor
0 Kudos

R,

Switch off availability check at schedule line category, this will confirm all qty.

Activate TOR at schedule line category, by this the requirement will transfer and can be seen in MD04.

TOR can work without ATP.