on 04-17-2015 10:59 AM
Hi Gurus,
When I am processing the work order, at final stage after TECO the actual cost is showing very high.
ex : If i use 2 labors for the work and paid 200/- each (only service work order) but when i execute the work it is showing as 3000/- in actual cost.
please help me how to fix this.
thanks
Hi VARA
Are you using internal labor for these expenses? If so, make sure your activity types carry the correct costs on them. Check transaction code KP26. Activity Rates are calcuklated for Cost Center-Activity Type couples for each financial period.
Regards
Savas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Provide screenshot for Operation tab and Cost tab of Order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.