on 04-17-2015 9:34 AM
While doing cutover activity what should be the status of the Open production order, open purchase order & open deliveries for sales.
We are using fixed bin for production staging so release production order etc it will not create transfer requirement.
So as per my understanding if I have open production order or purchase order then no issues.
Also I should not have any open delivery while migrating to wm.
Kindly confirm your views.
Are you planning to extend the warehouse for the existing plant+storage location combination if yes then you need to make sure that there is no document exist which activity needs to be carry forward in WM (e.g. Delivery document(inbound / outbound) , Production order due to staging of material (TR)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
what do you mean by "as I am using fixed bin in production staging"
Does this mean that you are not going to take into consideration the BOM quantity required from production order / process order ? or are you going to transfer a fixed quantity every time to the line side irrespective of the qty required by process order / production order
Relese order or pick order you set in the control cycle and these are material staging method. I suggest you go through with the below mentioned existing scn thread to get more detail
http://scn.sap.com/thread/3290305
Once you release production order then it creates TR which will have specific information like Warehouse number hence my suggestion would be that you should not release production order in the above scenario