Respected SD Experts,

We have Make to order strategy in our company. I have Sales order (MTO) quantity is 100MT, so by applying the 10% tolerance the dispatch can be done between 90MT to 110MT. Once we reach the dispatch quantity of 90MT or when 100 or 105 but i want no interruption till 110 , so system is not allowing any further dispatch. Please give guide me in this regard as soon as possible.


Best Regards,

Adnan

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

check in XD03 tab Shipping values Under and Overdelivery tolerance.

If reply solves your issue, please close the discussion.

Regards,

JM

former_member226334
Participant
0 Kudos

Dear Joan,

There is check on at customer master Overdelivery tolerance which is 10% and also check on for Underdelivery 10%. Is is possible to dispatch maximum, mean if quantity is 100 MT then system should not stop me before 110 but when i reached to 90 MT system automatically complete the line item. Please guide me in this regards,

Best Reagrds,

Adnan

Former Member
0 Kudos

Hi,

you may try in xd03, tab shipping, entry Partial delivery per item = B . You´ll be able to create a single delivery with material quantity ranging from 90 to 110 as per your tolerances and line item will be completed.