on 04-15-2015 2:40 PM
Dear Expert
I Have multiple PDS but I want to get only default PDS when Planning run takes place How to get it other than directly assigning priority in PDS Curto_simu . Is there any other way
Regards
Virender
Hello,
You can maintain the PDS priority in transaction PDS_MAINT,
Specifies the priority of a source of supply in source determination.
The highest priority is priority 0. Or you can use quota arrangement.
Apart from that you can lock the production version or change the validity date,
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Virender,
Assuming that you are using SNP Heuristics, one option is to maintain validity dates for each of the production versions for the PDS. For Example,
Prod Ver A : 04/15/2015 - 012/31/2015
Prod Ver B : 01/01/2016 - 12/31/2017 and so on...
The following link is helpful as well.
If you are using CTM, this can be handled by using the PDS of choice in the master data under planning scope.
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
15 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.