on 04-14-2015 2:46 PM
Hi
We are facing an issue with consumption of forecast in APO.
The product master "Backward/Forward Consumption Period" is CIF´ed from ECC system.
The problem is that 30 days is not necessary the same period in both systems:
In ECC the Consumption Period is in work days ( "Determines the consumption period in workdays" )
In APO the Consumption Period is in calendar days ( "Defines the consumption period in calendar days" )
Anyone familiar with this issue ?
Thanks
Claus Thielsen
Hi Claus,
From SAP help:
The consumption period is in calendar days not workdays. Since SNP and PP/DS
can use different calendars, it is not possible to define a calendar for use
with consumption. This may lead to unexpected results.
Maybe you can use the below BAdI
Sales orders consume forecasted quantities according to your own consumption
logic implemented via the Business Add-In (BAdI) /SAPAPO/DM_BADI_CSP.
Thanks,
Regards, Marius
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.