on 04-14-2015 12:32 PM
Hi,
Our Requirement is in ME38 which is for creting Schdule line Agrement the system should not allow to create schedule lines
if the Total of Schedule Line Quantity > Total Scheduled Quantity (Sum of all EKET-MENGE) > (EKPO-KTMNG) . I use MRP, so MRP generates schedule lines automatically. But my question is why it generates more schedule quantity than targed quantity (ekpo-ktmng)
Please, anybody knows how can I solve this problem?
Thanks.
See OSS note 83343 - *** MD01: No check of target qty in sched. agreemnt for background on this behavior and possible workarounds
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When you are using the scheduling agreement not sure why you are planning for a PO . ? Normally when you put this SA in the EKPO , the target quantity will become the total SA quantity and the schedule will be for individual quantity when they need to get delivered to the plant . and MRP will tell that only and once received the schedule line qty in the SA scheule line that line will be made GR..
But when i have checked , with a SA line for the EKET and EKPO, and the KTMNG is target value of the SA and EKET are the invidual lines for EKET - MENGE .
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks a lot for your reply raghavendra.
I don´t know if I have understood correctly your reply.
I have to use SA and PO together but it doesn´t matter this. The problem is when you put a target quantity in the Schedele Agreement the system doesn´t considered this amount as a maximun quantity to generate delivery scheules for a contract. The MRP generates all the requeriments planning for this material.
Do you know how colud solve this? We are in the ECC 6.0.
Regards,
Rosa
Hi,
Yes target quantity is a just the target quantity for the material in the SA .based upon the schedule maintained at SA38 and based upon the requirement system will go for the MRP calcylation . system treats the schedule line at SA38 as the available qty for the requirement qty for the date required .
Regards,