Building as statistical CO object?

Former Member
0 Kudos


Hi,

in our case there might be a need to post FI accounting documents or vendor invoices to buildings, which are later settled to certain cost centers.

I'm wondering if it is somehow possible to make the posting already so that the real posting goes directly to the cost center, but the building is used in the posting as a statistical object? 

Thanks in advance!

Accepted Solutions (1)

Accepted Solutions (1)

bowen_cao
Contributor
0 Kudos

Hi,

Seems no standard functionality, you will always need to maintain the settlement rule of the building.

Then you can settle the cost to cost center.

only one cost object can be actual, and only one cost object can be statistical object in settlement.

Regards,

Bowen