hi all,

i know what is transport target and i have done the same in the SLD and imported the objects in ID and

it is working fine ( our PI dev is PXD and test is PXT and they both have same sld)

we connected PXT system with EXQ system...

Now the testing is over and they want to test with another ECC system (EXT) .....so i have to connect PXT to EXT....

Do I need to add one more target in the transport target in SLD or I simply replace EXQ with EXT in the transport target?

Will the message go to both EXQ and EXT systems..

Accepted Solutions (1)

Accepted Solutions (1)

former_member182412
Active Contributor
0 Kudos

Hi Hema,

>>>>Do I need to add one more target in the transport target in SLD or I simply replace EXQ with EXT in the transport target?

You can replace transport target from EXQ to EXT in SLD and transport the objects again from Dev to QA then all your configuration objects will change to EXT then you will have both configurations available in PXT so you can receive the messages from both systems.

Regards,

Praveen.

former_member474221
Participant
0 Kudos

thanks for your helpful answer