Hi,
I have a synchronous service interface with req/response MTs. which had to be used in the BPMN. How should be the category? Or should I split it into 2 seperate interfaces one for req and the other for response and use outbound and inbound categories respectively?
Regards
Kalyan
Hi Kalyan
By BPMN I'm guessing you are referring to NW BPM (not ccBPM on dual stack).
The category will depends on how your BPM scenario looks like
1) Sender system --> NW BPM
For sender system - synchronous outbound service interface
For NW BPM - synchronous inbound service interface (with XI3.0 pattern)
2) NW BPM --> Receiver system
For NW BPM - synchronous outbound service interface
For receiver system - synchronous inbound service interface
The following two articles are useful to get you started on NW BPM
Rgds
Eng Swee
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.