on 04-08-2015 9:16 AM
Hello experts,
I have been making some tests and it seems that it is possible to control the project stock in one WBS element (MAT_PSPNR) and control the costs in other WBS element (PS_PSP_PSPNR). Is that correct? I mean that I'm controlling the MRP and the stocks of all the components in one WBS but the cost are set in other ones. Is there any problem working like this??
In my case the project is non-valuated stock and it seems that this scenario is ok, but what happens with valuated stock? Is it possible to work this way in this case?
Any comment or documentation about this topic would be appreciated.
Thanks in advance.
Laura
Hi,
If you are on ECC6 and EHP 03 i.e.SAP-APPL 603 and up, please activate business function switch OPS_PS_CI_1. One of the Enhancement in this Business Function is Determine WBS Account Assignment at MRP Area Level.
Please explore this functionality.
Hope it helps!
Thanks and Regards,
Varshal Kachole
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.