System is consuming future week forecast

Here is my scenario:

Creating sales order with RLD date 24-Apr-2015, when I do PGI of this order system saws this order qty as withdrawal qty in future week forecast at MD63. My requirement is system should consider current week forecast first before going to future week.

Can you please suggest how can I system to configure so it consume current week/period forecast first before going to future?

Attaching MRP3 and MD63 screen shot fyi. Reply appreciated.