GRC 10.1 Risk Analysis - Roles and Users do not exist

0 Kudos

Dear Experts,

On GRC 10.1, I have executed synchronization jobs and it finished successfully.

After that I tried to execute risk analysis but users/roles on ECC side do not exist.

Could you please help me what should I do?

Accepted Solutions (0)

Answers (4)

Answers (4)

Colleen
Advisor
Advisor
0 Kudos

Hi Nazli

I recommend you go back to basics and check through the Integration Framework setup to ensure you have properly defined your connectors. Also ensure the RFC connection and logical system has been configured.

Next up, check your RFC connection to see if the User Id in there unlocked and has sufficient access in the plug-in system.

Rerun all sync jobs for object repository and see if you get any result

Regards

Colleen

Former Member
0 Kudos

Hi Nazil,

Please check to make sure that the connector is linked to AUTH integration scenario. And also that the rules have been generated.

Thanks

Mukund

0 Kudos

Hi All,

We have already checked it.

Sync programs call itself, not ECC system this is the problem.

It should call ECC system, we create connector for ecc not grc.

Thanks

0 Kudos

Could you explain 'Sync program call itself'? At this point, I guess if you share the config steps you have performed end to end, it may help. Have you followed the below document?

0 Kudos

Hi Sajib,

This document is for GRC 10, but i am working on GRC 10.1

I have already checked it.

After executing synch jobs i do not find ECC users&roles on GRC side for risk analysis.

Thanks

Former Member
0 Kudos

Hi Nazli,

It seems the issue is with connector config.I  assume the job which is running the sync program is assigned the variant containing  appropriate connector (pointing to ECC system).

Regards,

Deepak

0 Kudos

Hi Deepak,

I checked the connector it is for ECC system not for GRC.

Thanks

Nazli

Former Member
0 Kudos

Hi,

Did you also check the job is running with the variant containing the connector?

Regards,

Deepak

0 Kudos

Hi Deepak,

Yes I checked it, it is working correct variant.

Thank

Nazli

Former Member
0 Kudos

Hi Nanzi,

Then without checking the actual config, It's difficult to say anything further. You should write to SAP about it.

Regards,

Deepak

0 Kudos

Nazil,

The document holds true for GRC 10.1 as well.

Former Member
0 Kudos

Hi Nazli,

did you check in t-code slg1? you can find problems related to data synch there.

Regards,

Deepak

0 Kudos

Hi Deepak,

There is one warning message for user sych;

User Adapter is empty

SP level is 0008, is it related with this?

Thanks

Nazli

0 Kudos

Hi Deepak,

I made some changes and executed the synch jobs again.

On SLG1 there is no any error/warning now.

But still output is empty.

Thanks

Nazli

Former Member
0 Kudos

Hi Nazli,

  Then I think there is some problem with configuration. Check this thread

May be helpful to you.

Regards,

Deepak

0 Kudos

Hi Deepak,

I found this one and checked my customizing.

I have already done Maintain Data Sources Configuration.

Thanks

Nazli

0 Kudos

Hi Nazil,

Did you check the synchronization job logs? That's where I would start to troubleshoot.

Also, the 1st sync should be a Full Sync.

Regards,

Sajib.

0 Kudos

Hi Sajib,

I executed as Full Sync.

And I checked the spool details of sync jobs and they completed successfully.

Thanks

Nazli

0 Kudos

Could you send a screenshot of the place where you found the problem? I think I am not clear on the problem. Is it when you run an ad-hoc risk analysis and in the output you see no result?
Please verify the below tables, you should have the users/ roles for the ECC system:

GRACUSERCONN

GRACRLCONN

GRACRLCONNT


0 Kudos

Hi Sajib,

This is the problem.

All synch jobs have been completed successfully but these tables do not have data.

Thanks