Dear All,

i wanna implement CTS+ on PI to transport non-abap objects , so  far i completed the following task

1. completed stms configuration

2. completed cts+ configuration

3. complete the transportation from d to q

but when i do the transport from Q to P, no target system in CR 's properties like showed in attached screen shot.

could anybody help me on this issue. your answer and reply would be great appreciated

Thanks a lot

Kevin Gao

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184720
Active Contributor
0 Kudos

>>>but when i do the transport from Q to P, no target system in CR 's properties like showed in attached screen shot.

This is because you have configured CTS+ only from D->Q

However are you sure you really want to export them again from Q -> P

Ideally, in order to maintain consistency(best procedure's) you should transport the same request from 

D-> Q -> P

You don't need to export/create the req again in Q to move it to P.

You can go to STMS -> Transport routes(SHIFT+F7) -> Configuration -> Standard Configuration -> Three Systems in Group.

Harish
Active Contributor
0 Kudos

Hi Kevin,

The CTS+ general configuration is required in all SAP boxes. Please refer the point 4 of below doc

http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20ccd0ec-2839-2b10-0097-828fcd8ed...

regards,

Harish

Former Member
0 Kudos

Hi Harish,

thanks for your linkage ,but i can't open it.

would you please verify that again?

Kevin Gao

Harish
Active Contributor
0 Kudos