when i go to SCC03 i fix the product ,operation sequence ,and then it asks me  " what this PPM  is meant for /for SNP or PPDS. then i state it is for PPDS  else SNP or both  .,anything relevant to SNP it is in terms of buckets ,but for PPDS it is in terms of minutes or hours,

what the above said is only my generic  reply?  but the client asked me a pointed  question -what is the difference between SNP PPM  and PPDS PPM ,???   i said PPDS PPM is used for resource planning,operations planning,activity planning but   SNP PPM is used for distribution ,deployment planning alone.

SNP heuristics does not do order based planning ,rather it does bucket planning/quantity planning based on source of supply ,say for location 1 ---30 quantities,location 2 -40 quan,-----DC--20 quan.

but he was not convinced with my answer....can you experts straighten the distorted answer.?

OHIO

"

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please refer this SAP useful help link with example,

Integrating SNP and PP/DS - Production Planning and Detailed Scheduling (PP/DS) - SAP Library

OSS note

481906 - SNP - PP/DS integration (documentation)

Best Regards,

R.Brahmankar

former_member205751
Participant
0 Kudos

thanks man,  got the rite link