Hi Friends,

 

i am having a doubt...

Let’s say in classic scenario

    

1) SHC created in SRM

2) PO replicated in ECC in Editable mode & in display
mode in SRM

Question 1:

If I change PO qty in ECC(as its in editable mode) will it get updated in SRM PO?(i.e changes we do in PO at ECC level will be updated in SRM?)

   

Question 2:

If I do Goods receipt & Invoice in ECC  for the same PO will it replicated in SRM as GC and Invoice against the PO?

Thanks,

San

Accepted Solutions (1)

Accepted Solutions (1)

konstantin_anikeev
Active Contributor
0 Kudos

Hi San,

there is no such scenario in SRM.

Classic means: SC in SRM and PO in Backend (Editable)

Extended classic: SC and editable PO in SRM, not editable PO in ECC

Regards

Konstantin

former_member504447
Active Participant
0 Kudos

Hi Konstantin,

Thanks for the resonse...

My question is..

In classic scenario we have editable PO in ECC & Non Editable PO in SRM(Display Mode) am i correct?

If i am correct...

Lets say in classic scenario i have created PO-XYZ for 100 Qty from SHC?It will be editable in ECC and non editable in SRM,so i go and change PO -XYZ qty in ECC as 80 qty or 120 qty,this changes we did in ECC will be updated in PO-XYZ available in SRM(in display mode)???

Similary

Lets say in classic scenario i have created PO-XYZ for 100 Qty from SHC?It will be editable in ECC and non editable in SRM,

I can do GR either in ECC or SRM? am i correct?

If i am correct..

If i do GR for a PO-XYZ in ECC,Is this update/follow on document(i.e GR posted for the PO) will be updated in SRM PO-XYZ(available in display mode) follow on document tab/History tab?

Thanks,

San

konstantin_anikeev
Active Contributor
0 Kudos

Hi San,

you do not have PO in SRM in classic scenario.

Regards

Konstantin

former_member504447
Active Participant
0 Kudos

Oh Ok....

You mean to say..
Once we created/Save SHC with Source of Supply...

PO will be created only in ECC?no document created in SRM(not even in dispaly mode)?? is it?

If it so..in classic scenario

Ho w we can check follow on documents for SHC(Created in SRM-Classic scenario) created in ECC or not?

Is there any link/identification exist between SHC created in SRM & PO creatred in ECC for the SHC?

Pls clarify me...

Thanks,
San

konstantin_anikeev
Active Contributor
0 Kudos

Hi San,

it is true. No SRM PO in classic scenario.

YOu can find PO number in the shoppong cart document on the tab "related documents" ( in position details )

Regards

Konstantin

former_member504447
Active Participant
0 Kudos

Thanks for the clarification..

I understood classic scenario now..

San.

former_member504447
Active Participant
0 Kudos

Hi Konstantin,

I have gone through some material,It says in Classic sceanrio Goods Confirmation & Invoice can be posted in SRM or ECC..

based on which document i can post GC in SRM as there is no PO in SRM for classic scenario?will be posted based on SHC?

Thanks,
San

Former Member
0 Kudos

You can post based on the Shopping Cart and reference of PO will be automatically available over there.

Thanks

Siddarth

konstantin_anikeev
Active Contributor
0 Kudos

Also SRM allows you to post GR to the PO's, created directly in ECC (without SC).

In both cases (by Siddarth and mine) GR will be created as a document in SRM and transferred to the ECC.