on 04-01-2015 1:11 PM
Hi Guys,
We are trying to upgrade from 8.8 PL 12 to 9.0 PL 15
During our database check process prior to upgrade. The process is stand still showing 27/50 in the upgrade wizard.
We found 2 Warnings and Error none and Status is processing as of now, but it is almost more than 6 hrs from start of process the status is same.
There are no errors found we have checked the LOG
Would like to know if anyone has an idea how long will it take to upgrade a 75 GB DB, RAM In our server is 128 GB
With Regards,
G. Eshvanth Singh
Hi,
as your DB size is large that's why it is taking time i recommend you to do not cancel the upgrade some times it takes more then 18 hrs .
--Manish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi guys
thanks for info it I have done the upgrade it took us about 26 to 30 hrs to finish the upgrade I have not included the time for error corrrections
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That is a large DB you should run the test run before you do the upgrade and split it between several days. Usually the testing should be 1/10 the time of an upgrade depending on the drive speeds and server configuration.
Usually the approved test XML file is good for a couple of days.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Eshvanth,
Hope the upgrade is done already. If it is not, you need to watch the progress and any additional errors. Your free disk space should be > 5 times of your current db.
Thanks,
Gordon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.