on 04-01-2015 8:11 AM
Team,
Am aware that in the BOM query we can add multiple items but in the quantity required the selection is single.
Eg; for the items A &B I have requirement for 5 for A and 10 for B , if am running BOM it will be based on item by item
Means I need to run BOM for item a with quantity 5 and item B with quantity 10 in the same time
Is it possible or in BOM or is there any other standard report in sap
Thanks to help.
Hello Vijesh,
In BOM explosion when you enter a required quantity, the system calculates the component quantity.
When you explode a multiple BOM, you enter either the required quantity or the alternative.
As per the SAP help,
The saddle support of a bicycle consists of the components seat pillar and tube.
If the base quantity is 1 piece, the component quantities are as follows:
Seat pillar: 1.000 piece
Tube : 0.250 M
If the required quantity is 200 pieces, the component quantities are as follows:
Seat pillar: 200.000 pieces
Tube : 50.000 M
Multiple requirement quantity is not possible you can develop the custom report by using BAPI
CS_BOM_EXPL_MAT_V2 multi level explosion, simular to CS12 functionality.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.