Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Workforce planning dates range.

Hello experts,

I am giving date planning period start and finish date range(01.04.2015 to 30.05.2015) in initial screen of CMP2 and trying to plan the resource for 60days, After executing I am able to see only the date range upto 19.05.2015. I tried many ways to extend the dates...but i am unable to do. The period unit is DAY in the settings.

Kindly check the screenshots. kindly suggest how to extend the date range in (workforce planning) CMP2 screen.

Is there any limited date range like only 50 days to be visible?

Thank you,



cmp2_2.PNG (45301 B)
cmp2_1.PNG (17462 B)

Hi Karthik,

in CMP2 or CMP9 even if we give the planning period start and finish dates more than 50 days. It will not show all the dates in the execution screen.

It will show only 50days in the execution screen. If you want to plan for the 52nd day, then you have to change the date range in the initial screen and execute. Then you will get the next date range in the execution screen. In same way you have to adjust the date range at initail screen to plan for the next days.

Lets see what other experts suggests.



1 View this answer in context
Not what you were looking for? View more on this topic or Ask a question