MD73 entering series of material numbers

Former Member
0 Kudos

The requirements plan and MRP controller are to very mixed. Is there a way to input a series of material numbers? Every time I paste in a series or range the system defaults to just one entry. Tips appreciated 🙂

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

In MD73 use Requirements Plan Number = * execute it.

Inside you can filter by using material numbers.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Thank you so much! Its the little things that really make a difference 😄