The requirements plan and MRP controller are to very mixed. Is there a way to input a series of material numbers? Every time I paste in a series or range the system defaults to just one entry. Tips appreciated 🙂
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
In MD73 use Requirements Plan Number = * execute it.
Inside you can filter by using material numbers.
Best Regards,
R.Brahmankar
Thank you so much! Its the little things that really make a difference 😄