Hello, Is there a way to force multiple deliveries creation with a specific "Actual GI Date" in VL10 ? I used Dialog button, but I have to change them one by one. i.e: I want to create all the deliveries with "27.03.2015" as "Actual GI Date" no matter of "Req. deliv.date" from sales orders / "Planned GI" from deliveries. Thank you.

Accepted Solutions (0)

Answers (2)

Answers (2)

0 Kudos

As there is no reply I tent to admit there is no standard way.

Lakshmipathi
Active Contributor
0 Kudos

If stock is available on the Requested Delivery Date, then the same would be your Actual GI Date.  Also, if the Requested Delivery Date is in the past and you create delivery on the current date during which stock is available, then system will consider the current date as Actual GI date.  This logic would work in VL10*.  If the foreground is not working, try with Background.

The other option is in sale order, you have a field "Service Rendered Date" at line item level.  There maintain the required date and execute VL10*

G. Lakshmipathi

0 Kudos

I have scenario where I must change Actual GI date for all current deliveries ( deliveries available in VL10).

i.e : I must have 31.03.2015 for all of them no matter of any other settings.

Is there any mass option to achieve it ?