Go Live Prep

Former Member
0 Kudos

Hello all

This is urgent.

What are the steps to be taken care of from security stand point when you are doing the go live prep and production support phases of implementation?

I would really appreciate quick responses

Thanks

2 REPLIES 2

Former Member
0 Kudos

Hi,

In the "Preparations for going live" phase you

- Plan going productive and install the necessary hardware and software for the production system;

- Create the user documentation;

- Train the users;

- Establish your system administration;

- Transfer the data and the system settings into your production system.

Please visit:

http://help.sap.com/saphelp_46c/helpdata/en/b0/ac94de8d49d111a4620060b03c3b0e/frameset.htm

Hope it helps.

Please award points if it is useful.

Thanks & Regards,

Santosh

Former Member
0 Kudos

Hi Jack,

On security point,

1.Change the default passwords for the user ids SAP* and DDIC in client 000 & 001.

2.Check if any user have unwanted authorization.

From administration point of view,

1.Prepare daily monitoring templates for BASIS and Application for day to day use.

2. Prepare guideline documents for all SAP activities and update it frequently.

Award points if it clears your query.

regards,

VInodh.