Manpower cost allocation issue

kandati_subramanyam
Participant
0 Kudos

Dear All,

I have an issue w r t manpower cost allocation issue and details of issue are mentioned in the attached excel.

Can anybody please throw some light on this issue

Regards

Su

Accepted Solutions (0)

Answers (1)

Answers (1)

iraladamodara_reddy
Active Participant
0 Kudos

Hi KTS

The option are :

1. If you Salary cost is posted to more than one cost centers, then you can allocate by Assessment Cycle the same based on  apportionment structure from Senders(CCA) to Receiver Object-WBS.

2.Based on Activity Rate calculation for each CC.

3.If all salary cost are Posted to 1 Cost Center only, then explore the option to  calculate common  rate to charge the receiver WBS elements.

4. Collect as Over head and charge  based on Over head rate.