Issue in which order plan cost 000 and order plan cost 001 are different

Former Member
0 Kudos

I was trying to make change to order plan cost 001 and make it the same as of 000 through the transaction cj9fs but for external projects having activities other than service activity no changes are being made to order plan cost 001. Please help.

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Hi Nitin,

Please check below SAP NOTE for more understanding:

Note 381430 - Copy plan version: Projects and orders

thanks

Sunil