EWM WAVE Management

Former Member
0 Kudos

I am processing my wave as a warehouse manager, which may contain over 100 items.  How do I know that the 100 items are completed (Picked, Packed and at the door).  I looked into the warehouse moniter, under wave (good issue, all three nodes) and none of them seem to give me information as to if my wave is completed.

It appears the wave number is entered in the work order task header for the task that were created for the wave, the wave number does not follow through to all new task to completion of the process.  Thus when I use warehouse monitor it does not pull up all of the task associated with the ODO, but only pulls the limited task  that were release with the creation of the task via /scwm/wave.

The question I am trying to answer is, How do I know when my WAVE is ready to be shipped?  

Accepted Solutions (0)

Answers (1)

Answers (1)

0 Kudos

Hi !

You can use shipping cockpit in NWBC for easy monitoring.