Hello Experts

i am working on support project here we did some enhancement like

we copied routine 301 and put some logic now i want to assign this new routine for STO PO to reference delivery type

so i want to know where we assign routine 301 for PO to outbond delivery

from SD point of view i know it is available in VTLA OR to Delivery

but from STO PO to outbond delivery please suggest where to maintain

Regards

Abhi

Accepted Solutions (1)

Accepted Solutions (1)

Shiva_Ram
Active Contributor

-Goto t.code 0VLK and select the delivery type used for the PO.

-Check the field Default order type and note the assigned value

-Then go to t.code VTLA and select the source document type that you found in the previous step and destination document that is used for PO.

-Then add the new routine that needs to be applied for the field you wish. Save the settings and test by creating a new PO-> Delivery.

Regards,

this is the correct answer. I have tried it in our project and it works.

Answers (2)

Answers (2)

former_member218251
Active Participant
0 Kudos

There is no copy control (and thus no usage of Routines) in this STO step.

You might be able to use the checking rule in the STO customizing (from SPRO: Material management > Purchasing > Purchase order > Set up stock transport order > Create checking rule).

If not, you will need to use a User Exit.

Former Member
0 Kudos

Can you give some more information for your requirement.

You can see in SPRO for STO PO to outbond delivery.

SPRO > MM > Purchsing > Conditions > Define Price Determination Process >

Define Schema Determination > Determine Schema for Stock Transport Orders >

enter for the combination of schema group purchasing organization .